The popular walking path around the Brick Reservoir will be off-limits for the next several months as the Brick Township Municipal Utilities Authority (MUA) begins a major infrastructure project aimed at increasing the reservoir’s usable water capacity and fortifying its long-term reliability.
The temporary closure will begin August 18 and last approximately 10 months, according to the Brick MUA. During this time, public access to the reservoir and surrounding recreational areas will be completely restricted for safety reasons.
The closure will allow for substantial improvements to the reservoir’s infrastructure, including lowering the water level and reinforcing the reservoir’s upper slopes to prevent erosion — a key issue that has limited its water storage capability.
“The upgrades will ensure the continued safety, reliability, and long-term sustainability of the reservoir and surrounding facilities,” the MUA said in a statement.
The work is being financed through a combination of federal and state sources. The New Jersey Infrastructure Bank (NJIB), which is helping to fund the project, says the current erosion limits usable storage to the top 5 feet of the reservoir (between 95 and 100 feet above sea level). The planned improvements will stabilize an additional 15 feet of slope (down to elevation 80), significantly expanding water capacity during times when the MUA cannot draw from the Metedeconk River.
The $7.967 million project involves removing the sand layer over the existing liner and installing a new protective system using geotextile fabric, gravel, and stone. These reinforcements aim to improve climate resilience, protect the local drinking water supply, and increase overall durability of the reservoir banks.
Funding sources for the project include $2.8 million from FEMA, and $942,000 from the NJ Resiliency Bank, plus an additional 10% contingency. Any remaining costs will be covered by financing through the New Jersey Water Bank.
The MUA said updates on the expected reopening will be posted on their website as the project progresses.
“We understand this may cause some inconvenience and appreciate your patience and cooperation as we complete this vital work,” officials said.

Any other walking paths in the area? 35mins or less?